- Construction of the 18,400 sq. ft. addition took place without disrupting Tufts Grinding’s production schedule.
- A fire sprinkler system was installed in the new building including a retro-fit into the existing building to meet current fire codes.
- A 7-1/2 ton capacity, heavy duty, double girder, top running crane with a 95 ft span was installed. Special structural engineering was used to create a large clear span opening into the existing building.
- 18,400 sq. ft.